The first three months has consisted of ground preparation such as removing old asphalt, clearing plumbing and sprinkler lines, and relocation of the phone lines. The ground was leveled and the foundation for the new addition has been poured. The north wall of the existing building has been removed and replaced with a temporary wall. The existing library building is scheduled for three-four months of remodeling and once completed, the temporary wall will be removed and the final floor plan will begin to take shape.
The project is thus far on schedule and is expected to be completed in December 2014.
-Sabrina Robertson
Nassau County Manager's Office