County Road 115 Construction Beginning November 25, 2019
Nassau County, Florida, November 21, 2019 – On Monday, November 25, 2019, work will commence for the long-awaited County Road 115 Widening and Resurfacing Project, from Henry Smith Road to Bypass Road.
The project will consist of milling and resurfacing of the existing lanes, widening the road approximately 1’ on both sides, construction of new 5’ paved shoulders, and reconstruction of ditches with cross drains and side drains. A contract for construction was awarded to Anderson Columbia at the September 23, 2019 Board of County Commissioner’s meeting.
The overall budget for the project totals $9,631,351 and is being paid for through a combination of Small County Road Assistance Program (SCRAP) and Small County Outreach Program (SCOP) Funding from the Florida Department of Transportation amounting to $8,999,026, in addition to $632,325 funding from the County.
The construction duration is 340 days but is subject to weather delays. It is anticipated that the project will be completed by November 2020.
*************************************************************************************************
Should you have any questions, please contact County Engineer, Robert Companion, at (904) 530-6225 or via email at [email protected].
NOTE: THE FIRST FEW WEEKS WILL CONSIST OF PRELIMINARY SITE WORK SO IT WILL BE SEVERAL WEEKS BEFORE ACTUAL CONSTRUCTION BEGINS. WE WILL SEND OUT NOTICES REGARDING POTENTIAL LANE CLOSURES IN ADVANCE SO RESIDENTS ARE AWARE OF ANY IMPACTS IT WILL HAVE ON THEIR DAILY COMMUTES.