Activities the week of September 7, 2026:
Drainage
- Box culvert construction ongoing
- Grading activities performed.
- Milling completed according to plans and specification.
- Worked on subgrade mixing
- Continued subgrade mixing and compacting Stas.36+65to 54+00
- Grading crew worked Stas.57+00 –88+00
- Continued to maintain traffic control in accordance with project plans and FDOT standards
- Conducted routine inspections of all signage, barrels, and devices to ensure proper placement and visibility
- Set up Type 3 barricades and signs for theCR121 road closure
- Minor adjustments are needed to maintain safety and traffic flow from Stations36+00 to 88+00.
Road Closure
Total closure began on Tuesday, September 8, 2026, from Balderdash Place to .33 miles South of Horseshoe Circle South.
Activities the week of September 14, 2026
- Box culvert construction operations
- Work on subgrade
- Cleaning activities through project area
- Continue preparing for mitered end sections and pipe placement
- Maintenance of traffic.
Planned dates/locations:
Monday, September 14, 2026
- Utilize lane closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement
- Continue box culvert (S-100/S-101) construction at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.).
Tuesday, September 15, 2026
- Utilize lane closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement
- Continue box culvert (S-100/S-101) construction at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.).
Wednesday, September 16, 2026
- Utilize lane closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement
- Continue box culvert (S-100/S-101) construction at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.).
Thursday, September 17, 2026
- Utilize lane closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement
- Continue box culvert (S-100/S-101) construction at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.)
Friday, September 18, 2026
- Utilize lane closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement
- Continue box culvert (S-100/S-101) construction at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.).
Saturday, September 19, 2026
- No work scheduled.
Sunday, September 20, 2026
- No work scheduled.
If you have any questions, please contact Capital Projects at (904) 530-6370.
-Sabrina Robertson
Communications Officer