Work performed the week of April 27, 2026:
Temporary Widening:
- Dressed up shoulder along temporary widening throughout project limits.
- Traffic was switched from left roadway to right roadway to allow for construction of the left roadway from Horseshoe Circle to .04 miles North of Batey LN (Sta. 221+25 to Sta. 238+75)
- Continue to operate from Horseshoe Circle to .04 miles North of Batey LN (Sta. 221+25 to Sta. 238+75)
- Remains in place from Horseshoe Circle to .04 miles North of Batey LN (Sta. 221+25 to Sta. 238+75)
- Milled existing asphalt 3” for depth from sta. 221+25 to 238+75 Lt. Rdwy.
- Subgrade was mixed from sta. 221+25 to 238+75 Lt. Rdwy.
Activities planned for the week of May 4, 2026:
- Continue subgrade operations from Horseshoe Circle to .04 miles North of Batey LN (Sta. 221+25 to Sta. 238+75)
- Road closure to be installed May 6th, 2026 from Stokes road to CR-119
- Box Culverts - May 6th, 2026
- Maintenance of Traffic.
Planned dates and locations:
Monday 05/04/26:
Continue working from Horseshoe Circle to .04 miles North of Batey LN (Sta. 222+00 to Sta. 238+69)
- Work operations will be behind barrier wall.
- Activities: grading and compacting subgrade Left Roadway
- Prepping for road closure from Stokes Rd to CR-119.
Tuesday 05/05/26:
Continue working from Horseshoe Circle to .04 miles North of Batey LN (Sta. 222+00 to Sta. 238+69)
- Work operations will be behind barrier wall
- Activities: grading and compacting subgrade Left Roadway, Paving Horseshoe Cir. South intersection
- Prepping for road closure from Stokes Rd to CR-119.
Wednesday 05/06/26:
Continue working from Horseshoe Circle to .04 miles North of Batey LN (Sta. 222+00 to Sta. 238+69)
- Work operations will be behind barrier wall
- Activities: grading and compacting subgrade Left Roadway
- Install road closure from Stokes Rd to CR-119.
Thursday 05/07/26:
Continue working from Horseshoe Circle to .04 miles North of Batey LN (Sta. 222+00 to Sta. 238+69)
- Work operations will be behind barrier wall
- Activities: Subgrade construction
- Maintain road closure and begin 3” milling operations from Stokes Road to CR-119
- Begin Demo of existing box culvert at sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119).
Friday 05/08/26:
Continue working from Horseshoe Circle to .04 miles North of Batey LN (Sta. 222+00 to Sta. 238+69)
- Work operations will be behind barrier wall.
- Activities: Paving L-1 lane from Sta. 222+00 to 238+69 Left Roadway.
- Maintain road closure and continue 3” milling operations from Stokes Road to CR-119
- Continue Demo of existing box culvert at sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119)
Saturday 05/09/26:
- No work scheduled
- Road closure continues.
Sunday 05/10/26:
- No work scheduled
- Road closure continues.
If you have any questions, please contact Capital Projects at (904) 530-6370.