Below are activities that took place the week of May 25, 2026:
Temporary Signals
- Removed temporary signals from Horseshoe Circle to .04 miles North of Batey LN (Sta. 221+25 to Sta. 238+75).
- Removed temporary barrier wall from Horseshoe Circle to .04 miles North of Batey LN (Sta. 221+25 to Sta. 238+75).
- See below for road closure
- CR 121 remains closed from Stokes Rd to CR 119 for construction of roadway and Concrete box culvert
- Continue box culvert construction
- Continued subgrade operations within road closure.
- Continue subgrade operations within road closure limits
- Begin asphalt base operations within road closure
- Continue box culvert operations at sta. 406+59
- Begin working from 0.38 miles North of Ground Hog PL to Horseshoe Circle S. (Sta. 90+40 to Sta. 106+71)
- Maintenance of traffic.
CR 121 from 0.38 miles North of Ground Hog PL to Horseshoe Circle S. (Sta. 90+40 to Sta. 106+71) will operate under single lane, two-way alternating traffic with temporary signals starting June 2, 2026.
Planned locations and dates:
Monday 06/01/26:
Road closure from Stokes Rd to CR 119
- Maintain road closure and continue road building operations from Stokes Road to CR-119
- Continue box culvert construction sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119).
Tuesday 06/02/26:
Begin working from 0.38 miles North of Ground Hog PL to Horseshoe Circle S. (Sta. 90+40 to Sta. 106+71)
- Work operations will be behind barrier wall
- Activities: Placing temporary signals and setting up barrier wall from Sta. 90+40 to 106+71
- Maintain road closure and continue road building operations from Stokes Road to CR-119
- Continue box culvert construction sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119).
Wednesday 06/03/26:
Continue working from 0.38 miles North of Ground Hog PL to Horseshoe Circle S. (Sta. 90+40 to Sta. 106+71)
- Work operations will be behind barrier wall
- Activities: Mill existing asphalt from Sta. 90+40 to 106+71 Right Roadway.
- Maintain road closure and continue road building operations from Stokes Road to CR-119
- Continue box culvert construction sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119).
Thursday 06/04/26:
Continue working from 0.38 miles North of Ground Hog PL to Horseshoe Circle S. (Sta. 90+40 to Sta. 106+71)
- Work operations will be behind barrier wall
- Activities: Begin subsoil excavation from sta. 92+12 to 102+13
- Maintain road closure and continue road building operations from Stokes Road to CR-119
- Continue box culvert construction sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119).
Friday 06/05/26:
Continue working from 0.38 miles North of Ground Hog PL to Horseshoe Circle S. (Sta. 90+40 to Sta. 106+71)
- Work operations will be behind barrier wall
- Activities: Continue subsoil excavation from sta. 92+12 to 102+13
- Maintain road closure and continue road building operations from Stokes Road to CR-119
- Continue box culvert construction sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119).
Saturday 06/06/26:
- No work scheduled
- Road closure continues.
·Sunday 06/07/26:
- No work scheduled
- Road closure continues.
If you have any questions, please reach out to the Capital Projects Department at (904) 530-6370.