Work performed the week of March 30, 2026:
- Drainage
- No drainage operation this week.
- Subgrade Prep
- Continued to blade and grade the outside left shoulder/ditch area for the temporary widening between Station 283+00 (4.67 miles) to 336+00 (5.67 miles) in preparation for asphalt
- Continued to blade and grade the outside left shoulder for the temporary widening between Station 56+00 (0.37 miles) to 72+00 (0.67 miles) in preparation for asphalt.
- Milling/Paving
- Placed 181.23 tons of asphalt for the temporary shoulder widening from Station 280+50 (4.62 miles) to 324+00 (5.44 miles) on the left shoulder
- Placed 163 tons of asphalt for the temporary shoulder widening from Stations 273+42 (4.48 miles) to 280+50 (4.62 miles), 222+13 ( 3.51 miles) to 222+42 (3.52 miles) and 76+35 (0.75 miles) to 107+85 (1.35 miles) .
- Upcoming work & activities the week of April 6, 2026:
- Continue to place the asphalt on the temporary widening
- Continue dress and sod operations
- Maintenance of Traffic.
Monday 04/06/26
- Continue temporary widening operation between 36+65 (0 miles) and 325+00 (5.46 miles).
During this operation, work will be conducted near the intersections of CR 121 with North/South Horseshoe Circle, Allie Sue Ln, Pattis Path, Cheyenne Ln, Batey Ln, Boyd Rd, Ethridge Lane, and Stokes Rd. There will be no impact to residents in this area, and traffic will be accommodated as necessary.
Tuesday 04/07/26:
- Continue temporary widening operation between 36+65 (0 miles) and 325+00 (5.46 miles).
During this operation, work will be conducted near the intersections of CR 121 with North/South Horseshoe Circle, Allie Sue Ln, Pattis Path, Cheyenne Ln, Batey Ln, Boyd Rd, Ethridge Lane, and Stokes Rd. There will be no impact to residents in this area, and traffic will be accommodated as necessary.
Wednesday 04/08/26:
- Continue temporary widening operation between 36+65 (0 miles) and 325+00 (5.46 miles).
During this operation, work will be conducted near the intersections of CR 121 with North/South Horseshoe Circle, Allie Sue Ln, Pattis Path, Cheyenne Ln, Batey Ln, Boyd Rd, Ethridge Lane, and Stokes Rd. There will be no impact to residents in this area, and traffic will be accommodated as necessary.
Thursday 04/09/26:
- Continue temporary widening operation between 36+65 (0 miles) and 325+00 (5.46 miles).
During this operation, work will be conducted near the intersections of CR 121 with North/South Horseshoe Circle, Allie Sue Ln, Pattis Path, Cheyenne Ln, Batey Ln, Boyd Rd, Ethridge Lane, and Stokes Rd. There will be no impact to residents in this area, and traffic will be accommodated as necessary.
Friday 04/10/26:
- Continue temporary widening operation between 36+ 65 ( 0 miles) and 325+00 (5.46 miles).
During this operation, work will be conducted near the intersections of CR 121 with North/South Horseshoe Circle, Allie Sue Ln, Pattis Path, Cheyenne Ln, Batey Ln, Boyd Rd, Ethridge Lane, and Stokes Rd. There will be no impact to residents in this area, and traffic will be accommodated as necessary.
Saturday:
- No work scheduled.
- No work scheduled.
-Sabrina Robertson