Work performed the week of May 4, 2026:
Temporary Signals:
- Continue to operate from Horseshoe Circle to .04 miles North of Batey LN (Sta. 221+25 to Sta. 238+75)
- Remains in place from Horseshoe Circle to .04 miles North of Batey LN (Sta. 221+25 to Sta. 238+75)
- Milled existing asphalt within road closure limits from Stokes Rd to CR 119
- Subgrade was graded and balanced from sta. 221+25 to 238+75 Lt. Rdwy.
- Horseshoe Cir. Was paved with (2) lifts of asphalt base
- CR 121 was closed from Stokes Rd to CR 119 for construction of roadway and Concrete box culvert.
Upcoming work & activities for the week of May 11, 2026:
- Continue 3” milling operations with road closure limits.
- Begin removing existing box culvert at sta. 406+59
- Relocating barrier wall and signals
- Maintenance of Traffic.
Dates and locations:
Monday 05/11/26:
Continue working from Horseshoe Circle to .04 miles North of Batey LN (Sta. 222+00 to Sta. 238+69)
- Work operations will be behind barrier wall
- Activities: Prepping subgrade for asphalt base and structural asphalt
- Maintain road closure and continue 3” milling operations from Stokes Road to CR-119
- Begin Demo of existing box culvert at sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119).
Tuesday 05/12/26:
Continue working from Horseshoe Circle to .04 miles North of Batey LN (Sta. 222+00 to Sta. 238+69)
- Work operations will be behind barrier wall
- Activities: Paving both lifts of Asphalt base in L-1 lane from Sta. 222+00 to 238+69 Left Roadway
- Maintain road closure and continue 3” milling operations from Stokes Road to CR-119
- Continue Demo of existing box culvert at sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119)
Wednesday 05/13/26:
- Continue working from Horseshoe Circle to .04 miles North of Batey LN (Sta. 222+00 to Sta. 238+69)
- Work operations will be behind barrier wall
- Activities: Paving structural asphalt from Sta. 222+00 to 238+69 Left Roadway
- Maintain road closure and continue 3” milling operations from Stokes Road to CR-119
- Continue Demo of existing box culvert at sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119)
Thursday 05/14/26:
Continue working from Horseshoe Circle to .04 miles North of Batey LN (Sta. 222+00 to Sta. 238+69)
- Work operations will be behind barrier wall
- Activities: Place final striping behind barrier wall from Sta. 222+00 to 238+69 Left Roadway
- Maintain road closure and begin 3” milling operations from Stokes Road to CR-119
- Continue Demo of existing box culvert at sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119)
Friday 05/15/26:
Continue working from Horseshoe Circle to .04 miles North of Batey LN (Sta. 222+00 to Sta. 238+69)
- Work operations will be behind barrier wall
- Activities: Begin relocating barrier wall to Sta. 90+40 to 106+71.
- Maintain road closure and continue 3” milling operations from Stokes Road to CR-119
- Continue Demo of existing box culvert at sta. 406+59 (approximately 1.34 miles North of Stokes Rd & .46 miles South of CR-119) .
Saturday 05/16/26:
- No work scheduled.
Sunday 05/17/26: