- 8/30/26 @ 7:30 p.m.
Activities that took place the week of August 24, 2026:
Drainage:
- Mitered end sections undergoing repair, preparation for pipe placement, preparation for box culvert installation ongoing.
- Began placing sod around box culvert S-201.
- A road closure began on Friday, August 28th, 2026, from Balderdash PL to .33 miles South of Horseshoe Cir. South until Tuesday, September 8th. Open to local traffic only.
- Placed two pallets of sod around the box culvert S201
- Continued fixing washouts throughout the project limits
- Conducted general site cleanup.
- MOT crew continues to maintain traffic control in accordance with project plans and FDOT standards
- Conducted routine inspections of all signage, barrels, and devices to ensure proper placement and visibility.
Mon. 08/31/26:
Utilize lane closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement
- Begin roadway construction activities in preparation for box culvert (S-100/S-101) installation at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.)
Tues. 09/01/26:
Utilize lane closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement
- Begin roadway construction activities in preparation for box culvert (S-100/S-101) installation at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.)
Wed. 09/02/26:
Utilize lane closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement
- Continue with roadway construction activities in preparation for box culvert (S-100/S-101) installation at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.)
Thurs. 09/03/26:
Utilize lane closures throughout project for mitered end sections and pipe placement.
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement
- Continue with roadway construction activities in preparation for box culvert (S-100/S-101) installation at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.)
Fri. 09/04/26:
Utilize lane closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement
- Continue with roadway construction activities in preparation for box culvert (S-100/S-101) installation at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.)
- NOTE: Access to properties will be maintained, and road will remain open to local traffic during this phase.
Sat. 09/05/26:
- No work scheduled.
Sun. 09/06/26:
- No work scheduled.
-Sabrina Robertson
Communications Officer