CR 121 subgrade construction Below is the weekly County Road 121 construction update.
Activities that took place the week of Oct. 26, 2026:
Road Construction:
Performed the following activities at temporary signal location (from Sta. 272+20 to Sta. 309+90)
- Grading
- Removal excess subgrade
- Compaction.
- MOT crew remained onsite throughout the day maintaining traffic in accordance with project plans and FDOT standards
- Traffic control devices, including signs, barrels, and barricades were maintained and adjusted as needed throughout each day to ensure proper placement and visibility
- The crew continues monitoring traffic control through the closure.
Activities planned for the week Nov. 2, 2026:
- Continue work behind low-profile barrier wall within signalized closure
- Cleaning activities throughout the project
- Continue to prepare for mitered end sections and pipe placement
- Perform project MOT operations per plan and specification.
Planned dates & locations:
Monday, Nov. 2, 2026
Work behind temporary signals and low-profile barrier walls.
- Begin paving operations in R-1 from Stas. 272+50 (4.47 miles north of the Duval County line and 3.02 miles south of CR 119) to 310+00 (5.18 miles north of the Duval County line and 2.31 miles south of CR 119)
- Utilize lane closures throughout project for mitered end sections and pipe replacement
- Activities: Mitered ends and pipe placement outside shoulders, sod placement.
Tuesday, Nov. 3, 2026
Work behind temporary signals and low-profile barrier walls.
- Continue paving operations in R-1 from Stas. 272+50 (4.47 miles north of the Duval County line and 3.02 miles south of CR 119) to 310+00 (5.18 miles north of the Duval County line and 2.31 miles south of CR 119)
- Utilize lane closures throughout project for mitered end sections and pipe replacement
- Activities: Mitered ends and pipe placement outside shoulders, sod placement.
Wednesday, Nov. 4, 2026
Work behind temporary signals and low-profile barrier walls.
- Complete paving operations in R-1 from Stas. 272+50 (4.47 miles north of the Duval County line and 3.02 miles south of CR 119) to 310+00 (5.18 miles north of the Duval County line and 2.31 miles south of CR 119)
- Utilize lane closures throughout project for mitered end sections and pipe replacement
- Activities: Mitered ends and pipe placement outside shoulders, sod placement.
November, Nov. 5, 2026
Work behind temporary signals and low-profile barrier walls.
- Reset and prepare temporary signals and low-profile barrier walls for work in L-1 from Stas. 272+50 (4.47 miles North of Duval County Line and 3.02 miles South of CR119) to 310+00 (5.18 miles North of Duval County Line and 2.31 miles South of CR119). Begin milling operations
- Begin subgrade operations
- Utilize lane closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement.
Friday, Nov. 6, 2026
Work behind temporary signals and low-profile barrier walls:
- Continue subgrade operations in L-1 from Stas. 272+50 (4.47 miles North of Duval County Line and 3.02 miles South of CR119) to 310+00 (5.18 miles North of Duval County Line and 2.31 miles South of CR119)
- Utilize lane closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement outside shoulders, sod placement.
Saturday, Nov. 7, 2026
- No work scheduled.
Sunday, Nov. 8, 2026
- No work scheduled.