Below is the weekly update for the County Road 121 construction project.
Activities that took place the week of September 14, 2026:
Drainage
- Box culvert construction ongoing
- Grading activities performed
- Worked on subgrade, mixing, grading and compacting.
Total closure began on Tuesday, September 8, 2026, from Balderdash Place to .33 miles south of Horseshoe Circle South.
Box Culvert construction
- Installed box culverts (S100 & S101) from Sta. 54+04 to Sta. 54+27
- Installed under-drain surrounding S100/S101, 4'' drainpipe at North and South of the box culvert 744321
- Began forming the footers for the wing walls and cutoff walls,
- Installed re-bar with previously installed concrete forms four wing wall footers at S-100 and S-101
- Tied steel for cutoff walls and bottom slab of 744321
- Conducted link slab operations at S-100 and S-101.
Road Construction
- Graded and compacted LT and RT roadwayatStas.36+65 to54+00and Sta.56+00 to Sta.88+00
- Dirt crew maintained compliance for local traffic and driveways, keeping them suitable for travelers
- MOT crew continues to maintain traffic control in accordance with project plans and FDOT standards
- Conducted routine inspections of all signage, barrels, and devices to ensure proper placement and visibility
- Set up Type 3 barricades and signs for theCR121 road closure
- Minor adjustments are made as needed to maintain safety and traffic flow from Stations36+00 to 88+00.
Activities planned for the week of September 21, 2026
- Continue box culver construction operations
- Continue road construction 54+00 – 88+00
- Cleaning activities throughout project area
- Continue preparing for mitered end sections and pipe placement
- Perform Maintenance of Traffic operations per plan and specification.
Planned dates and locations
Monday, September 21, 2026
Utilize land closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement, outside shoulders, sod placement
- Continue box culvert (S-100/S-101) construction at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.).
Tuesday, September 22, 206
Utilize land closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement, outside shoulders, sod placement
- Continue box culvert (S-100/S-101) construction at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.).
Wednesday, September 23, 2026
Utilize land closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement, outside shoulders, sod placement
- Continue box culvert (S-100/S-101) construction at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.).
Thursday, September 24, 2026
Utilize land closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement, outside shoulders, sod placement
- Continue box culvert (S-100/S-101) construction at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.).
Friday, September 25, 2026
Utilize land closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement, outside shoulders, sod placement
- Continue box culvert (S-100/S-101) construction at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.).
Friday, September 26, 2026
Utilize land closures throughout project for mitered end sections and pipe placement
- Activities: Mitered end sections and pipe placement, outside shoulders, sod placement
- Continue box culvert (S-100/S-101) construction at Station 54+14 (approximately .83 miles North US-90, and 1.0 mile south of Horseshoe Cir. S.)
Saturday, September 27, 2026
- No work scheduled.
Sunday, September 28, 2026
- No work scheduled.