Below is the weekly update on the Amelia Island Parkway/Buccaneer Trail Roundabout.
Activities that took place the week of Oct. 26:
- All final grading of roadside swales and sod placement is complete
- Power for the new light poles has been completed with FPL and the old light poles have been removed.
- Light fixtures installation
- Final asphalt paving is slated for Saturday, November 7th, and may continue into Sunday, November 8th, weather permitting.
Thermoplastic pavement markings will follow no less than 14 days after the friction course is placed to allow proper cure time.
Please watch for work crews and any short-term traffic control during weekend paving.
Thank you for your continued patience as we complete final paving and closeout.
Questions or concerns? Please contact Project Administrator Rafael Castro, KCI Technologies, at [email protected].
-Sabrina Robertson
Communications Officer
RSS Feed