Steady progress continues on the south leg despite some weather challenges this past week.
Activities completed the week of May 11, 2026:
- Drainage structure installation continued along the south leg of Amelia Island Parkway
- Limerock base mixing and grading advanced
- Embankment grading progressed around the perimeter of the roundabout in preparation for the shared-use path.
A few days of productivity were lost due to the much-needed rain, but the team made the most of the dry windows.
On a separate but related note, Segments 3 and 4 of the Amelia Island Parkway Trail (14th St roundabout to Bailey Rd; Bailey Rd to 8th St) are nearing completion at the end of May, and Segment 2 (14th St roundabout south to Jamestown Rd) is scheduled for completion in early July.
We’re not too far from this next phase of the Amelia Island Trail network opening! The AIP/Buccaneer roundabout will be the final link in this phase for the trail system tying the existing Segment 1 and new Segment 2 together.
As always, we appreciate the community for its patience and support as construction continues. If you have any questions, please contact the Capital Projects Department at (904) 530-6370.